摘要 以辽沈地区的某工程为例,在现场试验的基础上,结合数值模拟计算软件对等截面抗拔桩的承载特性进行了分析,结果表明开挖将导致坑内土体产生卸荷回弹,从而带动抗拔桩回弹,桩身上下部分分别承受正、负摩阻力,并在桩身产生轴向拉力,同时,桩土界面法向应力降低,导致桩的极限抗拔承载力降低。 Taking some project in Liaoning and Shenyang as the example, the paper combines the numeric simulation calculation software to analyze the loading capacity features of uniform section uplift piles, proves by the result that the excavation will lead to the unloading rebound in pit soil which will lead to up-lift pile rebound, indicates the upper and lower parts of the pile can bear the positive and negative frictional resistance while the axial tensile force can be formed in the piles, and indicates the decreasing force of pile-earth interface method which will cause the decrease of the pile' s extreme uplift pile' s loading capacity.
作者 乔云航
出处 《山西建筑》 2015年第13期59-60,共2页 Shanxi Architecture
关键词 抗拔桩 承载力 数值模拟 uplift pile, loading capacity, numeric simulation
  • 相关文献

参考文献5

二级参考文献38

  • 1杨敏,周洪波,杨桦.基坑开挖与临近桩基相互作用分析[J].土木工程学报,2005,38(4):91-96. 被引量:134
  • 2廖俊展,黄茂松,王卫东,陈峥.设置抗浮抗拔桩深基坑的三维数值仿真分析[J].岩土工程学报,2006,28(B11):1370-1373. 被引量:22
  • 3郑刚,颜志雄,雷华阳,雷扬.基坑开挖对临近桩基影响的实测及有限元数值模拟分析[J].岩土工程学报,2007,29(5):638-643. 被引量:147
  • 4王卫东,翁其平,吴江斌.上海世博500kV地下变电站超深抗拔桩的设计与分析[J].建筑结构,2007,37(5):107-110. 被引量:23
  • 5POULOS H G,CHEN L T,Pile response due to unsupported excavation-induced lateral soil movement[J].Canadian Geotechnical Journal,1996,33(6):670-677.
  • 6POULOS H G,CHEN L T.Pile response due to excavation-induced lateral soil movement[j].Journal of Geotechnical and Geoenvironmental Engineering,ASCE,1997,123(2):94-99.
  • 7LEUNG C F,CHOW Y K.Behavior of pile subject to excavation induced soil movement[J].Journal of Geotechnical and Geoenvironmental Engineering,ASCE,2000,126(11):947-954.
  • 8LIM J K SHEN R F,CHOW Y K.Behavior of pile groups subject to excavation-induced soil movement[J].Journal of Geotechnical and Geoenvironmental Engineering,ASCE,2003,129(1):58-65.
  • 9ONG DE L,LEUNG C F,CHOW Y K.Pile behavior due to excavation-induced soil movement in clay.I:stable wall[J].Journal of Geotechnical and Geoenvironmental Engineering,ASCE,2006,132(1):36-44.
  • 10ONG DE L,LEUNG C F,CHOW Y K.Pile behavior due to excavation-induced soil movement in clay.II:collapsed wall[J].Journal of Geotechnical and Geoenvironmental Engineering,ASCE,2006,132(1):45-53.

共引文献117

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部