摘要 目前国内超高层核心筒施工常用的模板体系有自爬模和顶升钢平台系统。结合工程实例,针对超高层核心筒混凝土结构模板体系的搭设、使用、爬升等过程进行多角度探讨,对常用的自爬模和整体顶升钢平台系统在技术、安全、造价、进度等方面进行对比,总结各模板体系的优缺点,为超高层核心筒模板施工给出建议。 At present, the construction of high-rise core tube formwork system includes automatic climbing formwork and lifting steel platform. Based on engineering practice, this paper analyzed the different high-rise building core tube formwork systems by installation, using, climbing and so on. By comparing automatic climbing formwork with lifting steel platform in technology, safety, cost, schedule, this paper summarized the advantages and disadvantages of each formwork system. This paper gave some useful advice in selecting formwork system of super high-rise building core tube.
出处 《施工技术》 CAS 北大核心 2015年第7期11-13,16,共4页 Construction Technology
关键词 高层建筑 核心筒 模板 自爬模 顶升钢平台 施工技术 tall buildings core tube formworks automatic climbing formwork lifting steel platform construction
  • 相关文献

二级参考文献5

共引文献31

同被引文献55

引证文献8

二级引证文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部