摘要
通过分析中海油大厦(深圳)项目基坑开挖施工过程中,由于基坑施工引起的临近深圳地铁2号线隧道的沉降与位移风险,采取系统的评价、监测和管控等有效应对措施,探讨该项目基坑开挖对地铁风险的成功应对经验。详细介绍了施工方案中的防控措施、监测方案以及施工过程中的处置措施。
Based on analysis of evaluation, monitoring and control measures adopted in foundation excavation for settlement and displacement control in a project in Shenzhen, this paper introduced the experience of risk control in foundation excavation in the project. Control measures, monitoring scheme and treatment measures were introduced in detail.
出处
《施工技术》
CAS
北大核心
2015年第7期77-82,86,共7页
Construction Technology
关键词
地铁
基坑
风险
监测
subways
foundation excavation
risk
monitoring