通过对斜拉桥结构原理的分析,在高大悬挑梁施工上引入该施工工艺,解决了高大悬挑梁施工搭设脚手架的困难,为高大框架作业提出了一种新的施工方法。
Through the analysis on the cable-stayed bridge structure principle, introduced the construction technology to tall cantilever beam con- struction, solved the problems of tall cantilever beam construction erecting scaffold, provided a new construction method for tall cantilever beam operation.
出处
《山西建筑》
2015年第14期89-90,共2页
Shanxi Architecture
关键词
悬挑梁
斜拉桥
工艺
工程
cantilever beam, cable-stayed bridge, technology, engineering