摘要
重庆某工程位于长江与嘉陵江交汇处。其在人工挖孔桩施工中,遇到了很厚的卵石层。卵石塌方严重,紧挨卵石处护壁成悬空状态,危及到了孔内作业人员的人身安全,导致无法成孔。本文主要介绍了卵石人工挖孔桩施工技术成孔经验,可供类似工程借鉴。
A project in Chongqing is located in the Yangtze River and Jialing River interchange. In the construction of ma-nual bored pile, builders encountered a thick layer of cobbl-estone. The cobblestone col apses seriously, and the retaining wal closely to the gravel is at hanging state, which endangers workers’ safety, thus the holing is a failure. This paper mainly introduces the experience of construction technology of man-ual bored pile of cobblestone which can be used for reference for the similar project experience.
出处
《城市建筑》
2014年第30期96-96,共1页
Urbanism and Architecture
关键词
卵石
挖孔桩
施工
cobblestone
bored pile
construction