摘要
根据麻家梁矿井主立井井筒所穿过岩层的工程地质条件,分析了井筒施工方法的选择和井壁结构的设计,并根据矿井建设规模及选定的提升设备,对井筒断面布置进行了优化。
Based on the engineering geological condition of strata where the main shaft passes in Majialiang mine, the paper presents the engineering method selection and wall structure design. In addition, the section layout of the shaft is optimized in the light of construction scale and selected hoisting equipment.
出处
《山西煤炭》
2015年第2期18-20,共3页
Shanxi Coal
关键词
大直径立井
厚冲积层
冻结法
井壁结构
井筒断面布置
large diameter main shaft
thick alluvium
freezing method
structure of shaft wall
section layout of shaft