摘要
通过多工艺动力头钻机和空气潜孔锤钻进工艺相结合,克服了施工水井过程中遇到的施工困难,解决了严重缺水地区村民的生活用水问题。为今后在类似缺水地区施工提供了宝贵的施工经验。
Through the combination of the process of driving head drill and DTH hammer drilling technology, overcome the dififculties encountered in the process of construction the construction of wells, to solve the problems of the villagers living water in the serious water shortage area, which provides valuable construction experience For the similar water shortage area construction.
出处
《山东煤炭科技》
2015年第5期175-177,共3页
Shandong Coal Science and Technology