摘要
以长沙地铁1号线一期工程下穿建筑物施工为实例,介绍盾构隧道下穿建筑物时控制地层沉降的主要措施及掘进参数的控制。
Taking the underpass building construction of Changsha Metro Line 1 Phase I Project as a case,the article introduces the main measures to control the stratum settlement and the control of tunneling parameters when the shield tunnel underpasses the buildings.
出处
《城市道桥与防洪》
2015年第4期189-191,共3页
Urban Roads Bridges & Flood Control
关键词
盾构法
建筑物
参数控制
地层沉降
shield process,building,parameter control,stratum settlement