摘要 目前,全国中小水利项目中的泵站、节制闸、船闸相比交通、铁路项目中的交通桥跨数较少且跨径较短,如若采用预制后架设,安全和资金上面投入的代价相比较大。本文结合仪征套闸除险加固工程这一实例,就套闸上闸首交通桥的实际情况,结合一系列理论验算依据,对其上闸首启闭机工作桥成功地进行了现浇,希望可以为中小型水利项目类似工程施工提供借鉴和参考。 At present, pumping station, check gate and lock of national small and medium - sized water conservancy projects have less spans and shorter span diameter compared with traffic bridges in transportation and railway projects. If they are erected after prefabrication, price of investing in safety and fund is higher. In the paper, the example of Yizheng suite lock risk elimination and reinforcement project as well as actual condition of traffic bridge on the head of suite lock are adopted. A series of theoretical calculation basis is combined for the the successful cast-in-situ of hoist working bridge on the gate head. It is expected that it can provide reference for similar constructions in small and medium-sized water conservancy projects.
出处 《水利建设与管理》 2015年第5期64-67,36,共5页 Water Conservancy Construction and Management
关键词 仪征套闸工程 脚手架 支撑 验算 Yizheng simple lock project scaffold support verification
  • 相关文献

参考文献4

  • 1JGJ130--2001建筑施工扣件式钢管脚手架安全技术规范[S].2001.
  • 2JGJ59-99建筑施工安全检查标准[S],1999.
  • 3JGJ80-91.建筑施工高处作业安全技术规范.,1991..
  • 4DG/TJ08-016-2004钢管扣件水平模板的支撑系统安全技术规程[S].2004.