无底柱放矿中岩石提前混入原因分析及预防措施 被引量:4

Reason of causing advanced rock mixed in ore in no-pillar ore drawing and its preventive measures
下载PDF
导出
摘要 岩石的提前混入使得矿石过早贫化,研究分析发现导致镜铁山矿桦树沟矿区岩石提前混入的主要原因是推排、大块卡堵放矿漏斗、不合理的出矿方法以及端部放矿废石移动规律。本文结合镜铁山矿的实际生产经验对这4种导致岩石提前混入的主要原因的作用机制进行分析,提出对应的预防措施。 The advanced rock mixed in ore made the ore dilution early. The study and analysis found that the main reason of causing advanced rock mixed in ore in Huashugou mining area of Jingtieshan mine were unbroken ore wall, bulk jammed hopper, unreasonable ore drawing way and the waste moving law in the end discharge. In this paper, combined with the production practice of Jingtieshan mine, the action mechanism of advanced rock mixed in ore was analyzed, and the preventive measures were put forward.
出处 《中国矿山工程》 2015年第3期33-37,共5页 China Mine Engineering
关键词 无底柱分段崩落法 岩石提前混入 推排 端部放矿废石移动规律 sublevel caving without sill pillar advanced rock mixed in ore unbroken ore wall waste moving law in the end discharge
  • 相关文献

参考文献7

二级参考文献14

共引文献26

同被引文献65

引证文献4

二级引证文献26

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部