通过冶炼过程控制钢水纯净度,连铸过程控制过热度,铸坯加热过程控制均热温度等措施,采用连铸生产的AAR M-101 F钢满足技术协议要求,试制成功。
The molten steel purity is controlled during smelting process, and superheat degree is controlled during continuous casting process, and soaking temperature is controlled during casting billet heating process, and AAR M- 101 F steel produced by continuous casting can meet the requirements of technical agreement and achieve successful tri- M production.
出处
《大型铸锻件》
2015年第3期49-51,共3页
Heavy Casting and Forging
关键词
AAR
M-101
F钢
连铸
车轴
AAR M-101 F steel
continuous casting
trial production