通过虎头山隧道洞口大变形处治,分析变形产生的危险源和对工期的影响,阐述了变形处治的具体方案和注意事项,结合处治过程提出了变形处治的原则性措施。
Through processing of Hutou mountain tunnel portal large deformation, it analyses of deformation of hazards and the impact on the time limit for a project, expounds the eoncrete scheme of deformation treatment and matters needing attention, the deformation principle of treatment measures are put forward combined with the treatment process.