摘要
飞来峡电厂1#主变压器保护装置因超期服役、双重化配置要求和省网安评考核需要等原因进行技术改造。该文介绍了本次技改方案的内容,重点阐述方案对新增保护装置选型、配置的技术要求和具体实施过程,点明本次技术改造起到设备更新换代、提高安全系数和满足新形势需要的效果。
Feilaixia power plant 1#main transformer protection device for overterm service, double configuration requirements, and the province may be a review of the assessment need to wait for a reason technical renovation.The technical scheme and the content of the emphasis on solutions for new protection device selection and configuration of technical requirements and specific implementation process have been introduced.The technical transformation equipment upgrading, safety coefficient improvement and the needs of new situation have been pointed out as well.
出处
《广东水利水电》
2015年第4期68-71,共4页
Guangdong Water Resources and Hydropower
关键词
飞来峡电厂
1#主变
保护装置
技术改造
Feilaixia power plant
1# main transformer
protection device
technical transformation