摘要
以延长石油科研中心项目工程为实际案例,详细介绍钢管混凝土柱大截面环梁施工工艺。在分析钢管混凝土环梁施工难点、重点的基础上介绍环梁节点施工过程中的施工方法和控制要点。同时在实施过程中运用了BIM技术模拟整个环梁的施工过程,最终达到了良好的施工效果。
Taking Yanchang Petroleum Headquarters Tower for example, the authors introduce the construction technology of ring beam joint of large cross section on the concrete filled steel tubular column. The concrete filled steel tubular column ring beam construction difficulties and key points are analyzed as basis to introduce the construction method and control points on the process of ring beam joint. Meanwhile, the application of BIM technology is applied to simulate the construction process of the ring beam in the process of implementation. Ultimately, the good construction effect is achieved.
出处
《施工技术》
CAS
北大核心
2015年第10期25-27,共3页
Construction Technology
关键词
高层建筑
钢管混凝土柱
环梁
节点
施工技术
tall buildings
concrete filled steel tubular column
ring beam
joints
construction