摘要
介绍襄阳北编组站增建上行系统工程中实施编组站综合自动化设计方案,特点是结合既有编组场改建,从系统方案、主要设备的设置、接口设计、设备利旧、工程实施几个方面进行简述和总结,为与之类似工程提供一点借鉴。
Based on the analysis of the renovation to the existing marshalling station, this paper describes technical solution of the comprehensive automatic control system for Xiangyang North Station in term of overall system scheme, configuration of maior equipment, design of interfaces, re-use of the existing equipment as well as engineering construction, which could offer reference for similar projects.
出处
《铁道通信信号》
2015年第5期14-17,共4页
Railway Signalling & Communication
关键词
改建铁路
编组站综合自动化
设计方案
系统构成
接口
Renovation of the existing railway
Comprehensive automatic control system of ter-minal marshalling station
Design solution
System structure
Inter{ace