期刊文献+

强涌浪开敞海域大直径钢管桩自浮运卸船技术 被引量:2

Unloading large diameter steel tubular piles from vessel by self-floating in open seas with huge surges
下载PDF
导出
摘要 文章以委内瑞拉卡贝略新集装箱码头项目钢管桩自浮运卸船施工为实例,分别对大直径钢管桩在强涌浪海域自浮运卸船方案的制定、实施及卸船过程中遇到困难、问题的解决方法进行了分析和探讨,可为同类工程提供参考和借鉴。 Taking the unloading technology of steel tubular piles from vessel by self-floating in Puerto Cabello new container terminal project of Venezuela as an example, we analyzed and discussed the formulation and implementation of unloading large diameter steel tubular piles from vessel by self-floating in huge surges waters, and the solutions of the difficulties and problems in the process, which can provide references for similar projects.
出处 《中国港湾建设》 2015年第6期61-64,共4页 China Harbour Engineering
关键词 强涌浪 开敞海域 钢管桩 自浮运 卸船 huge surges open seas steel tubular pile self-floating discharging
  • 相关文献

参考文献3

  • 1委内瑞拉卡贝略港新集装箱码头工程基础设计报告[R].广州:中交第四航务工程勘察设计院有限公司,2013.
  • 2委内瑞拉PuertoCabello新集装箱码头项目整体波浪数学模型研究报告[R].广州:华南理工大学,2012.
  • 3Foundation solutions for projects harbor construction[M]. Luxem- bourg: Arcelor-Mittal, 2007.