摘要
峰林洼地地貌石灰石矿山矿量分散,基建采准工作面的确定难度大,对平寨石灰石矿进行了综合分析,确定了首采区位置,并提出了两套基建采准工作面方案,进行了比较和分析,确定了合理的基建工作面布置方案,为峰林洼地地貌露天石灰石矿在首采区基建采准工作面的布置方面提供了宝贵经验。
Resource distribution of limestone quarry with many hills and depression geomorphology is disperse,it is difficult to deter- mine construction mining work thee.Ping Zhai limestone quarry is comprehensively analyzed in this paper, then determing the location of the first mining area,and propose two plan for construction mining work face,which have been compared and analyzed.So it is deter- mined that/he arrangement plan of mining work face ,which provides valuable experience for construction mining work face of the first mining area in limestone quarry with many hills and depression geomorphology.
出处
《水泥工程》
CAS
2015年第3期87-89,共3页
Cement Engineering
关键词
露天石灰石矿
首采区
基建采准工作面
limestone quarry
first mining area
construction mining work face