某电站进水口闸墩滑框倒模模板变形原因分析

Analysis of Deformation of Pier Sliding Frame Mold Template in a Hydropower Station
下载PDF
导出
摘要 某工程采用滑框倒模施工技术对水电站进水口闸墩进行施工时,发生局部模板变形现象,导致闸墩上、下层混凝土之间出现"错台"、"挂帘",单层混凝土出现竖向及水平向变形、闸墩截面尺寸加大等质量问题,直接影响混凝土的浇筑质量。经分析,模板体系设计强度、刚度不足是问题出现的主要原因,可供同类施工借鉴。 A project adopts the sliding box reverse mold construction technique for hydropower station water inlet sluice pier construction, local template deformation phenomenon, lead to the pier, the lower concrete between the " faulting of slab ends ", "curtain", the concrete in the vertical and horizontal deformation, the pier cross-section size increase the quality problems, directly affect the quality of concrete pouring. Through the analysis of the template system design strength, stiffness shortage is the main reason for the problem.Reference in the similar construction.
出处 《人民珠江》 2015年第3期63-65,共3页 Pearl River
关键词 电站进水口工程 模板变形 模板设计 混凝土浇筑质量 Power plant water intake project Template deformation Template design Quality of concrete pouring
  • 相关文献

参考文献6

  • 1DL/T5110—2000水利水电工程模板施工规范[S].
  • 2DL/T5400-2007水工建筑物滑动模板施工技术规范[S].
  • 3宋光明,汪永剑.北江大堤西南水闸墙体模板施工技术[J].人民珠江,2013,34(4):60-62. 被引量:2
  • 4晏正根,吴国如,揭新.滑框倒模施工工法[C]//2009-2010年度水利水电工程建设工法汇编,2011.
  • 5GB50214-2001组合钢模板技术规范[S].
  • 6GB50017-2003,钢结构设计规范[S].

二级参考文献3

  • 1GB50017-2003钢结构设汁规范[S].
  • 2DL/T5110-2000.水利水电工程模板施工规范[S].[S].,..
  • 3GB50214-2001 组合钢模板技术规范[S].

共引文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部