摘要
主要分析了JLQ45 t-45 m轨道式重箱门式起重机主梁的制作工艺特点、工艺过程、关键技术及制作步骤。提出了主梁制作工艺中需要改进和注意的细节,解决了制作成型后出现的一些质量问题,为今后门式起重机主梁制作和检验提供借鉴。
This article main analyzes the characteristics of the production process JLQ45t -45m rail heavy box gird- er gantry crane. The processing know -hows and key technologies involved are discussed. The specifics that need to be improved or carefully considered are identified for such gantry crane girders to be successfully fabricated. Some quality problems after the product is shaped are resolved. The practice may be viewed as future reference for fabrication and testing of gantry crane girders.
出处
《港口装卸》
2015年第3期35-38,共4页
Port Operation
关键词
门式起重机
工艺分析
主梁
拱度计算
gantry crane
process analysis
girder
camber calculation