大型风电场有功控制能力测试试验研究

Active Power Control Ability Testing Method for Large-scale Wind Farms
下载PDF
导出
摘要 风电大规模、快速接入电网给电网有功调度和控制带来新的挑战,而且中国的风电测试工作,还仍处于刚起步的阶段,国内无试验规程可以借鉴。在甘肃省电力科学研究院"甘肃酒泉汇能风电开发有限公司桥西第三风电场有功控制能力测试试验"基础上,文中给出了一套对于MW级风电场有功控制能力测试的实验方法与流程,为提升风电接入电网的安全可靠性提供技术支撑奠定了基础。 Rapid connection of wind power to power grid in large scale brings a new challenge to the active power dispatch. However, the wind power testing in China is still at an initial stage, thus no existing test procedure can be referenced. Based on the Gansu Electric Power Research Institute's Active Power Control Testing Experiment in the Third Wind Power Plant of Jiuquan Huineng Wind Power Development Co., Ltd., Gansu Province, this paper proposes a new testing method and process for MW-grade wind power active control test to provide a basis for improving the reliability of the connection of wind power to power grid.
出处 《高压电器》 CAS CSCD 北大核心 2015年第6期27-30,共4页 High Voltage Apparatus
基金 国家电网科技项目(5227221350BR 5227221300XP 52272214002Y)~~
关键词 风电场 有功控制 风电测试 可靠性 wind power plant active power control wind power test reliability
  • 相关文献

参考文献5

  • 1刘宝华,钟洪明.华能甘肃瓜州安北第三风电场330kV升压站顺利通过并网前验收[EB/OL].http://news.bjx.tom.cn/html/20140825/540196.shtml, 2014-08-25.
  • 2Q/GDW392-2009风电场接入电网技术规定[S].国家电网公司,2009.
  • 3Q/GDW630-2011风电场功率调节能力和电能质量测试规程[S],2011.
  • 4甘肃电网风电调度管理规定(试行)[EB/OL].http://www.doe88.corn/p-646530777665.html,2013-07-12.
  • 5李雪明,行舟,陈振寰,陈永华,王福军,罗剑波.大型集群风电有功智能控制系统设计[J].电力系统自动化,2010,34(17):59-63. 被引量:50

二级参考文献8

共引文献72

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部