以石佛寺水库供水计量装置实施方案为例,论述了计量井选址、土建施工工艺、流量计选型等方面的内容,说明一切施工方案应从工程实际情况出发,因地制宜,集思广益,采取科学有效的施工措施,保证工程顺利实施。目前井室防渗效果良好。
Implementation plan of water supply metering device in Shifosi Reservoir is adopted as an example for discussing metering well site selection, civil construction process, flow-meter model selection and contents in other aspects. It is obvious that all construction plans should be based on actual condition of the project, measures suiting local conditions should be adopted, useful ideas are absorbed, scientific and effective construction measures are adopted, thereby ensuring smooth implementation of project. The anti-seepage effect of well chamber is excellent at present.