摘要 水电站机械设备复杂,要求的安装精度较高,而水轮发电机组作为整个工程的核心,其安装质量直接关系到设备以后的运行效率。本文以阔克塔勒水电站水轮发电机组为例,对其安装步骤和工艺要点进行了说明,意在为类似工程提供参考。 Hydropower station machines and equipment are complex,which requires higher installation precision.The installation quality of hydroelectric generation set,as the core of the whole project,is directly related to operation efficiency of equipment in the future.In the paper,Kuoketale Hydropower Station hydroelectric generation set is adopted as an example for describing installation steps and key technology points,thereby providing reference for similar projects.
作者 许建述
出处 《中国水能及电气化》 2015年第6期41-43,共3页 China Water Power & Electrification
关键词 阔克塔勒水电站 水轮发电机组 工艺要求 分析 Kuoketale Hydropower Station hydroelectric generation set technological requirements analysis
  • 相关文献

参考文献6

  • 1刘坤,李明,等.发电工程项目施工管理的探讨[J].山东电力技术,2005(5):35-36.
  • 2康胜军.机电安装发展研究及安装管理战略[J].中国科技信息,2010(10):12-14.
  • 3王凤坤.施工企业项目管理规范化建设[J].施工企业管理,2008(5):16-18.
  • 4王卫红.中国水力发电工程(机电卷)[M].北京:中国电力出版社,2008(5):5638.
  • 5邱治国.水电站发电机组安装工艺[J].四川水利水电,2010(6):4547.
  • 6王鹏.福建省永安西门水电站机电及金属结构安装[J].水利科技,2008(4):40-42. 被引量:3