摘要
通过蜻蛉河双线特大桥27#、28#承台施工实例,对3500m3超大体积混凝土连续浇筑的技术措施、温控措施、机械设备配置以及材料贮备等施工中存在的重难点问题进行阐述和总结,为同类工程的施工提供参考和借鉴。
Take Qingling River double track grand bridge 27 #,28 # as construction practice,important and difficult issues in the construction of 3500m3 large volume of concrete continuous casting have been expounded and concluded,including technical measures,temperature control measures,disposition of mechanical equipment and material storage,providing reference for similar project.
出处
《北方交通》
2015年第6期28-31,共4页
Northern Communications
关键词
承台
大体积混凝土
施工组织
温控
连续浇注
技术措施
Supporting platform
Large volume of concrete
Construction organization
Temperature control
Continuous casting
Technology measures