摘要
由于芦村二号煤矿副斜井斜长较长,辅助提升量大,提升工况复杂,故设计合理的副斜井提升系统成为了保证矿井安全高效生产的关键问题之一。通过计算、分析和方案比较对提升设备进行了选型并确定了提升系统,为解决该矿的副斜井提升问题提供了合理性建议。
Because of The long dip length of the vice inclined shaft in Lucun NO.2 Coal Mine,there is a large amount of complex auxiliary hoisting. As a result of that,The design of a reasonable vice inclined shaft hoisting system has become one of the key issues to ensure safe and efficient production of the mine.According to the hoisting equipment selection by calculation,analysis and scheme comparison,the hoisting system is definitely settled in this article.
出处
《装备制造技术》
2015年第6期213-216,共4页
Equipment Manufacturing Technology
关键词
煤矿
副斜井
提升系统
双钩提升
单绳缠绕式提升机
coal mine
vice inclined shaft
hoisting system
double hook hoisting
single rope winding hoist