摘要 在重复性建设项目过程中,学习效应是一种很常见的现象。但目前还没有研究将学习效应应用到重复性项目的工期与成本优化问题中。本文将学习效应考虑到重复性项目最低成本问题中,分析了学习效应对项目成本的影响,建立了考虑学习效应的项目总成本模型,并设计了一种改进的粒子群算法进行求解。算例表明,学习效应有助于缩短项目工期、节约成本。本文研究有利于项目计划人员充分利用学习效应制定更为合理的进度方案。 The phenomenon of the learning effect is very common in repetitive construction projects.However,it has not been considered in the time / cost trade-off analysis. In this paper,the cost optimization problem in repetitive construction projects with the learning effect was studied,while meeting a prescribed deadline. The influence of the learning effect on the total project cost was analyzed,and then the mathematical formulation of the current problem was proposed. In order to solve this problem,an improved PSO algorithm was designed. The effectiveness of the proposed algorithm was verified by an illustrative example and the result indicates that considering the learning effect in scheduling provides more potential to reduce project duration and cost. The research presented in this paper can help the planner to establish a more realistic and reasonable planning.
出处 《土木工程与管理学报》 北大核心 2015年第2期54-59,共6页 Journal of Civil Engineering and Management
基金 国家自然科学基金(71171079 71271081)
关键词 学习效应 重复性项目 最低成本问题 learning effect repetitive construction projects cost optimization problem
  • 相关文献

参考文献25

  • 1Harris R B,Ioannou P G. Scheduling projects with re- peating activities [ J ]. Journal of Construction Engi- neering and Management, 1998,124(4) :269-278.
  • 2Lucko G. Productivity scheduling method:Linear sched- ule analysis with singularity functions [ J ]. Journal of Construction Engineering and Management, 2009,135 (4) :246-253.
  • 3张立辉,邹鑫,乞建勋.通过延迟阶跃函数求解重复性项目控制路线的方法研究[J].中国管理科学,2013,21(3):118-126. 被引量:4
  • 4Kallantzis A, Soldatos J, Lambropoulos S. Linear ver- sus network scheduling: a critical path comparison [ J ]. Journal of construction engineering and management, 2007,133 (7) :483-491.
  • 5Zhang Lihui ,Pan Chuyun ,Zou Xin. Criticality compari- son between the repetitive scheduling method and the network model[ J ]. Journal of Construction Engineer- ing and Mana-gement ,2013,139(10) :135-141.
  • 6张立辉,邹鑫,乞建勋.考虑软逻辑的重复性项目离散时间费用权衡问题[J].系统工程学报,2013,28(4):554-561. 被引量:10
  • 7Hyari K H, E1-Rayes K, E1-Mashaleh M. Automated trade-off between time and cost in planning repetitive construction projects [ J ]. Construction Management and Economics ,2009,27 (8) :749-761.
  • 8Georgy M E. Evolutionary resource scheduler for linear projects [ J ]. Automation in Construction, 2008, 17 (5) :573-583.
  • 9Tang Y, Liu R, Sun Q. Study and Application on China Railway Construction Project Scheduling Model Based on Resource Leveling [ M ]. Berlin : Springer Berlin Heidelberg, 2013.
  • 10De P,James Dunne E, Ghosh J B,et al. The discrete time-cost tradeoff problem revisited [ J ]. European Journal of Operational Research, 1995,81 ( 2 ) : 225- 238.

二级参考文献36

  • 1Harris R B, Ioannou P G. Scheduling projects with re- peating activities[J]. Journal of Construction Engineer- ing and Management, 1998, 124(4): 269-278.
  • 2Kallantzis A, Soldatos J, Lambropoulos S. Linear ver- sus network scheduling: a critical path comparison[J]. Journal of Construction Engineering and Management, 2007, 133(7): 483-491.
  • 3Kallantzis A, Lambropoulos S. Correspondence of activ- ity relationships and critical path between time-location diagrams and CPM [J]. Operational Research, 2004, 4 (3): 277-290.
  • 4Yamin R A, Harmelink D J. Comparison of linear scheduling model(LSM) and critical path method(CPM) [J-]. Journal of Construction Engineering and Manage- ment, 2001, 127(5): 374-381.
  • 5Arditi D, Tokdemir O B, Suh K. Effect of learning on line-of-balance scheduling[J]. International Journal of Project Management, 2001(19): 265-277.
  • 6O' Brien J J. VPM scheduling for high-rise buildings [J]. Journal of the Construction Division, ASCE, 1975, 101 (CO4), 895-905.
  • 7RedaR M. RPM: repetitive project modeling[J]. Jour- nal of Construction Engineering and Management, 1990 116(2) : 316-330.
  • 8Mahdi I M, A new LSM approach for planning repetitive housing projects [J]. International Journal of Project Management, 2004, 22 : 339- 346.
  • 9Harmelink D J, Rowings J E. Linear scheduling mod- el: development of controlling activity path[J]. Journal of Construction Engineering and Management, 1998, 124(4) : 263-268.
  • 10Lucko G, Orozco A A P. Float types in linear schedule analysis with singularity functions[J]. Journal of Con- struction Engineering and Management, 2009, 185 (5) : 368-377.

共引文献11

同被引文献4

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部