摘要
龙岩国际商贸中心工程在施工中,根据工程施工条件和结构特点,对混凝土结构的后浇带分别采用无缝施工和超前止水技术。无缝施工技术的应用有效地控制了超长结构混凝土裂缝的开展;超前止水技术的应用避免了后浇带留置期间地下水的渗入。
Longyan International Trade Center is under construction. According to the construction conditions and characteristics, the seamless construction and advanced water sealing technology for concrete structures were adopted respectively. The application of seamless construction technology can effectively control the super long concrete structure crack, avoid the infiltration of groundwater in the retention period of post pouring belt, and thus achieve good social and economic benefits.
出处
《闽西职业技术学院学报》
2015年第2期117-119,共3页
Journal of Minxi Vocational and Technical College
关键词
混凝土
后浇带
膨胀加强带
超前止水
无缝施工
concrete
post pouring belt
expansion reinforcing band
advanced water sealing
seamless construction