期刊文献+

藤桥水厂改扩建工程一体化净水池设计 被引量:4

Design of Integrated Water Purification Tank in Tengqiao Waterworks
原文传递
导出
摘要 在用地异常紧张的情况下,将絮凝沉淀过滤工艺设计成一体化净水池且与清水池叠合建设。介绍了一体化净水池结构形式、施工中注意事项和近5年来的运行情况,结果表明,该设计工艺合理,投资节省,施工进度快;可供用地受限或者工期要求高的小型水厂设计参考。 Under the condition of extreme land shortage, flocculation, sedimentation and filtration processes were designed in an integrated water purification tank which was superimposed on the treated water tank. The structural form of the integrated water purification tank, matters needing attention in the construction and the operation in the last five years were introduced. The results showed that the design had advantages of reasonable process, low investment and fast construction speed, which could provide reference for design of small-scale waterworks with limited land or short construction period.
机构地区 温州
出处 《中国给水排水》 CAS CSCD 北大核心 2015年第14期87-89,共3页 China Water & Wastewater
关键词 一体化净水池 设计 施工 运行 integrated purification tank design construction operation
  • 相关文献

参考文献3

二级参考文献12

共引文献14

同被引文献15

引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部