摘要
以某露天矿为例,对各个采区接续方案进行分析,最终确定重新拉沟过渡方案,在此基础上通过比较转向过渡期间剥采比、过渡时间、过渡期间剥离物综合运距等技术要素,确定最佳采区接续位置,为类似露天矿采区接续研究提供参考。
Taking a certain open-pit mine as the example, the author analyzes the connecting schemes of various mining areas, and eventually determines the forming ditch transition scheme. On this basis, through comparing the stripping ratio, transition time,stripping comprehensive transportation distance technology elements during the transition period, the article determines the optimal mining area connection location, which provides a reference for similar open-pit mining area connection research.
出处
《露天采矿技术》
CAS
2015年第7期10-13,共4页
Opencast Mining Technology
关键词
露天矿
采区接续
位置确定
open-pit mine
mining area connection
location determination