摘要
水电站多具有长泄水道、大落差发电特点,对于这类电站单级消能工已经不能满足安全和经济要求,因此,宜采用多级消能。本以大河边水库为研究对象,针对溢洪道原设计方案中的不利水力现象进行了方案修改,取得了良好效果。
Hydropower station is mostly characterized by long sluiceway and big drop power generation. Single-stage energy dissipation work of the power station can not meet requirement on safety and economy. Therefore,multi-stage energy dissipation can be suitably adopted. In the paper,Dahebian Reservoir is adopted as a research object,plan is modified aiming at adverse hydraulic phenomenon in original design plan of spillway with excellent effect.
出处
《中国水能及电气化》
2015年第7期51-54,共4页
China Water Power & Electrification
关键词
大河边水库
溢洪道
多级消能
优化
Dahebian Reservoir
spillway
multi-stage energy dissipation
optimization