摘要
由于岩巷大坡度上山巷道施工普遍存在职工无操作经验、管理人员缺乏管理经验,施工中极易发生伤人事故,同时施工质量得不到保证等现象。为了解决大坡度上山施工中存在的问题,需要打破常规施工方法,对岩巷大坡度上山施工工艺进行优化。提出了优化方案,分析了施工效果,并成功实施。
Aiming at the phenomenon of workers without operation experience, management personnel lack of experience,the high hid- den danger construction, and the quality not be guaranteed in the construction of large slope updip in rock drift,to solve the problems in the construction of large slope updip,it needs to break the conventional construction method, and optimize of the construction technology of large slope updip in rock drift. Optimization scheme was proposed in the paper, and construction effects were analysed, the implement of the technology has achieved good effects.
出处
《中州煤炭》
2015年第7期67-68,83,共3页
Zhongzhou Coal
关键词
大坡度
工程质量
优化方案
large slope updip
project quality
optimization scheme