发电机进相试验是机组商运前需要考核的重要试验之一,试验数据将作为今后发电机进相运行的重要依据。发电机进相运行存在一定风险,通过试验数据说明了方家山2号发电机组具备相应的进相运行能力。
Leading-phase operation test shall be done before the commercial operation of generator.The test data is very important in future operation of the generator under-excitation.There is certain risk in the test.The test date illustrates the fangjiashan 'generator has the ability of leading-phase operation.
出处
《科技视界》
2015年第24期96-97,共2页
Science & Technology Vision
关键词
发电机
进相运行
低励限制
失磁保护
Generator
Leading-phase operation
Minimum-excitation limit
Loss-of-excitation protection