Sun Paper tissue base paper production line put into operation successfully on June 16th,2014.The tissue base paper plant began construction in August 2013,and all of construction work was completed in November 2013.The production line began installation officially in January 2014,the key equipment of the production line Yankee dryers installed smoothly on May 16th,the production line entered into the commissioning phase.
Sun Paper tissue base paper production line put into operation successfully on June 16th,2014.The tissue base paper plant began construction in August 2013,and all of construction work was completed in November 2013.The production line began installation officially in January 2014,the key equipment of the production line Yankee dryers installed smoothly on May 16th,the production line entered into the commissioning phase.