摘要
结合对多个电厂专用线设计实例,对铁路翻车机卸车系统的工作原理、电厂站作业流程进行了介绍,并对翻车机卸车能力计算及电厂站卸车能力计算进行了阐述,结合工程案例,给出了一些电厂站总图布置建议。
Combining with various power plant special line design examples,the paper introduces working principles of railway tippler unloading system and power plant station operation procedures,describes tippler unloading capacity computation and power plant station unloading capacity computation,and shows some general power plant distribution suggestions by combining with engineering cases.
出处
《山西建筑》
2015年第24期220-222,共3页
Shanxi Architecture
关键词
翻车机
作业流程
卸车能力
电厂站布置
tippler
operation procedure
unloading capacity
power plant station distribution