某药厂污水处理系统沉淀池改造研究探讨 被引量:1

Study and Discussion of Reform of Sedimentation Tank in Waste Water Treatment System for Pharmaceutical Plant
下载PDF
导出
摘要 对某药厂因产能扩大导致出水量增加,沉淀池改造问题进行了分析,提出了解决方案,根据提出的解决方案分别试验其实际效果,选出了改平流沉淀池为斜板沉淀池的方法作为改进方法,计算出了适应本项目需要的斜板倾角等参数,提出了平流沉淀池改斜板沉淀池的注意事项。 The water discharge in one plant became larger in view of expansion of production capacity. The problem in the reform of sedimentation tank was analyzed, and then some solving measures were proposed. With these measures the tests were carried out so as to check their effects, from which the scheme of using tilted plate to replace flat plate in tank was selected. The proper tilt angle was calculated, and the notices in the reform with replace of titled plate to fiat one were presented.
出处 《化工与医药工程》 2015年第4期23-25,共3页 Chemical and Pharmaceutical Engineering
关键词 沉淀池 斜板 去除率 沉速 sedimentation tank tilted plate removing rate settling rate