摘要
针对500 kV智能变电站投产调试阶段中发现的问题进行阐述,对缺陷总结分析,对出现的问题的原因进行剖析,对调试工作的重要性进行说明,并针对性地提出了智能变电站二次验收方案。
In this paper,the common problems of secondary equipment in intelligent substation on the stage of debugging and commissioning are clarified. The defects of secondary equipment are summed up and analyzed. The reasons of those problems are analyzed,and the importance of the debugging work is illustrated. Better acceptance plan are proposed about secondary equipment of intelligent substation.
出处
《山西电力》
2015年第4期47-48,共2页
Shanxi Electric Power
关键词
智能变电站
调试
虚端子
SCD文件
intelligent substation
commissioning
virtual terminal
SCD document