期刊文献+

新疆小山口二级电站引水渠道工程设计 被引量:1

The diversion canal engineering design of Xinjiang Xiaoshankou secondary hydropower station
下载PDF
导出
摘要 新疆小山口二级电站地处新疆严寒地区,引水渠道沿线地形起伏,高度变化较大。同时,工程区覆盖层多为砂砾石层,基岩多为泥岩、砂质泥岩等,覆盖层渗透性强,基岩具有较强的冻胀性和膨胀性。在进行渠道设计时,应考虑排水、防渗、保温及抗冻胀等工程措施,重点介绍了小山口二级电站引水渠道的工程设计内容。 The Xiaoshankou secondary hydropower station is located in the cold region in Xinjiang. The terrain fluctuation along the canal is big. The overburden is mostly sand gravel and the bed rocks are mudstone and sandy mudstone in the project area,the permeability of overburden is strong and the bed rocks have strong frost heave and expansion. So during the canal design,the engineering measures of drainage,anti-seepage,hot insulation and anti-expansion should be considered. This paper mainly introduces the diversion canal design content.
作者 丁旭
出处 《水科学与工程技术》 2015年第4期43-45,共3页 Water Sciences and Engineering Technology
关键词 二级电站引水渠道 砂质泥岩 抗冻胀工程措施 the diversion canal of secondary hydropower station sandy mudstone engineering measures against frost heave
  • 相关文献

参考文献5

  • 1SL/205--97,水电站引水渠道及前池设计规范[S].
  • 2GB50286-98.堤防工程设计规范[S].[S].,..
  • 3SL23-91.渠系工程抗冻胀设计规范[S].[S].,..
  • 4SLl8-2004,渠道防渗工程技术规范[S].
  • 5SL/T31--1998,聚乙烯(PE)土工膜防渗工程技术规范[S].