摘要
文章通过沿黄公路巴拉贡北互通立交钢箱梁桥的施工实践,阐述了钢箱梁-预应力混凝土悬臂梁组合结构的施工技术,并对主要的施工质量控制关键点进行了分析,有效地保证了钢混组合结构的施工质量,为同类型组合结构工程提供了施工经验。
During the construction of Balagong north interchange bridge in along Yellow River primary highway, these paper formulated the construction technology of composite structure for steel box grider-prestressed concrete projecting beam, and analyzed the committed step of main quality control.It could guarantee construction quality of the composite structur of steelconcrete, which provided construction experiences for similar engineerings.
出处
《现代交通技术》
2015年第4期57-59,共3页
Modern Transportation Technology
关键词
钢箱梁
预埋件
悬臂梁
组合结构
施工技术
steel box grider
inserted piece
projecting beam
composite structure
construction technology