依托江苏海洋观测平台项目,在外海永久性平台的施工过程中,针对外海极其恶劣的气象条件,对墩台和观测室的常规施工方案进行优化,采取陆上整体预制、海上安装的施工工艺,大大缩短了主体工程的施工周期,可为类似外海平台工程提供借鉴。
During construction of the permanent offshore platform in Jiangsu offshore observation platform project, to counter the extremely harsh weather condition, we carry out an optimization of the conventional construction scheme for the abutment and the observation house, and adopt the construction technology of integral prefabricating on land and installing at sea, by which the construction period of the main part of the project is greatly shortened . The optimized construction technology may serve as reference for similar projects concerning the offshore platform engineering.
出处
《水运工程》
北大核心
2015年第8期78-80,共3页
Port & Waterway Engineering
关键词
外海平台
整体预制
海上安装
offshore platform
integrated prefabrication
marine installation