摘要
瀑布沟水电站自投运以来,推力油槽存在油雾过多的问题,机组受到油雾的严重污染。通过分析油雾产生的原因,提出了治理油雾的方案,实施结果表明:机组油雾问题有所改善,但未根治。
From the commissioning of Pubugou Hydropower Station, excessive oil mist is observed in the thrust oil groove, which seriously contaminate the generator unit. Reasons of such problem are analyzed. Treatment measures are then proposed. Practice shows that the excessive oil mist is mitigated but vet fully solved with these measures.
出处
《水电与新能源》
2015年第8期65-67,共3页
Hydropower and New Energy
关键词
瀑布沟
推力油槽
油雾
治理方案
Pubugou Hydropower Station
thrust oil groove
oil mist
treatment scheme