单管高压旋喷防渗墙在布坑水库除险加固中的应用 被引量:3

Application of single tube high pressure jet grouting impervious wall in risk removal and reinforcement of Bukeng Reservoir
下载PDF
导出
摘要 漳州市芗城区布坑水库除险加固工程采用单管高压旋喷墙作为大坝防渗方式。本文对其主要参数要求、施工程序及工艺、检测结果等进行分析。结果表明,该技术防渗质量较好,可作为类似水库大坝防渗加固的有效措施之一。 Zhangzhou Xiangcheng Buke Reservoir risk removal and reinforcement project adopts single tube high pressure jet grouting wall as dam seepage control mode. in the paper, main parameter requirements, construction procedure and process, test results, etc. are analyzed. Results show that the technology has excellent seepage control quality. It can be used as one of effective measures of dam seepage prevention reinforcement in similar reservoirs.
作者 朱平火
出处 《水利建设与管理》 2015年第8期66-68,71,共4页 Water Conservancy Construction and Management
关键词 布坑水库 除险加固 单管注浆 防渗墙 Bukeng Reservoir risk removal and reinforcement single pipe grouting impervious wall
  • 相关文献

参考文献2

  • 1DL/T5200-2004,水利水电工程高压喷射灌浆技术规范[S].
  • 2袁光裕,胡志根.《水利工程施工》[M].第5版.北京:中国水利水电出版社,2009.