考虑风险传导情形的交货延迟风险评估方法 被引量:1

Evaluation method for backorder risk by considering risk propagation
下载PDF
导出
摘要 针对交货延迟风险可能沿供应链向下游企业传导的情形,提出一种考虑风险传导情形的交货延迟风险评估方法。依据故障树分析思想,将制造商交货延迟事件视为故障树分析的顶上事件,综合考虑供应链中各级供应商的供求关系和风险传导的情形,构建了由多级供应商的采购、生产、运输延迟等中间事件和基本事件构成的制造商交货延迟故障树;通过分析相关历史事件确定了故障树中各基本事件发生的概率,并依据故障树分析原理计算制造商交货延迟事件发生的概率;综合考虑制造商交货延迟事件发生造成的损失及制造商可能得到的来自供应商的补偿,评估了制造商的交货延迟风险。通过算例说明了所提方法的可行性与有效性。 Since the backorder risk might spread to the downstream enterprises along the supply chain, a risk evalua- tion method for backorder risk by considering the risk propagation was proposed. In this method, the manufacturer delayed in delivery was treated as the top event in fault tree according to FTA idea. The fault tree included middle e- vents of multiple suppliers such as procurement, production and transportation and basic events of manufacturer backorder was constructed by considering the supply and demand between enterprises and the risk propagation. The probabilities of basic events in the fault tree were determined through the analysis of related historical events. The backorder probability of manufacturer was calculated according to FTA idea. On this basis, the backorder risk of manufacturer was evaluated by considering the loss caused by manufacturer backorder and the compensation of man- ufacturer obtained from the suppliers. A practical example was used to illustrate the feasibility and validity of the proposed method.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2015年第8期2191-2200,共10页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(71271051 71371002) 中央高校基本科研业务费资助项目(N120506001)~~
关键词 风险评估 供应链 风险传导 交货延迟 故障树分析 risk evaluation supply chains, risk propagation backorder fault tree analysis
  • 相关文献

参考文献21

  • 1LI L. The role of inventory in delivery time competition[J]. Management Science, 1992,38(2) : 182-197.
  • 2LEDERER P J, LI L. Pricing, production, scheduling, and delivery-time competition[J]. Operations Research, 1997,45 (3) :407-420.
  • 3SHIN K S, SHIN Y W, KWON J H, et al. Development of risk based dynamic backorder replenishment planning frame- work using Bayesian Belief Network[J]. Computers ~ Indus- trial Engineering, 2012,62(3) : 716-725.
  • 4于辉,陈剑,于刚.批发价契约下的供应链应对突发事件[J].系统工程理论与实践,2006,26(8):33-41. 被引量:80
  • 5GALASSO F, MERCE C, GRABOT B. Decision support for supply chain planning under uncertainty [J]. International Journal of Systems Science, 2008,39(7) : 667-675.
  • 6GUILLAUME R, GRABOT B, THIERRY C. Management of the risk of backorders in a MTO-ATO/MTS context under imperfect requirements[J]. Applied Mathematical Modelling,2013,37(16/17):8060 8078.
  • 7RODGER J A, PANKAJ P, GONZALEZ S P. Decision mak- ing using a fuzzy induced linguistic ordered weighted averaging approach for evaluating risk in a supply chain[J]. International Journal of Advanced Manufacturing Technology, 2014, 70 ( 1- 4):711 723.
  • 8WATSON H A. Launch control safety study[M]. Murray Hi- ll, N.J., USA:Bell Telephone Laboratories, 1961.
  • 9WINKLER R L, POSES R M. Evaluating and combining physicians' probabilities of survival in an intensive care unit [J]. Management Science, 1993,39 (12) : 1526-1543.
  • 10GIGERENZER G, HOFFRAGE U. How to improve Bayes ian reasoning without instruction: frequency formats[J]. Psy- chological Review, 1995,102 (4) : 684-704.

二级参考文献39

共引文献111

同被引文献12

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部