摘要 针对五强溪水电厂5号机组上导摆度偏大问题,利用机组稳定性在线监测系统的录波、计算、分析功能,实施机组的变转速、变励磁、变负荷试验,采用多种方法进行分析,得出发电机转子质量不平衡是导致5号机组摆度偏大的主要原因的结论。 Aiming to large numerical value of upper guide throw for Wuqiangxi Hydropower Plant NO. 5 unit,several stability tests including variable speed test,variable excitation test and variable load test are independently designed and implemented by making use of the recording,calculation,analysis function of hydropower unit stability online monitoring system by a variety of methods. Through the above measures,the conclusion are drawn that the generator rotor mass imbalance is the main reason of large numerical value of upper guide throw for NO. 5 unit.
出处 《湖南电力》 2014年第5期26-28,31,共4页 Hunan Electric Power
关键词 上导摆度 在线监测 变转速 变励磁 变负荷 upper guide throw online monitoring variable speed variable excitation variable load
  • 相关文献

同被引文献28

引证文献4

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部