摘要
本文结合国家电网输电线路防灾技术实验室的1000kV交直流环氧树脂胶浸纸绝缘穿墙套管的结构特点,提出现场吊装工艺,详细介绍现场配重、起吊、重心调整、就位后套管旋转对孔等主要过程,并分析吊装过程中存在的问题及解决方法。
Based on structural characteristics of 1 000 kV AC /DC epoxy resin impregnated paper insulation wall bushing,this paper puts forward its site hoisting process,introduces the main process in detail,such as the site additional weight,lifting,shifting the central gravity,casing rotation in place,and analyzes the existing problems and solutions in the process of hoisting.
出处
《湖南电力》
2014年第5期46-48,共3页
Hunan Electric Power
关键词
1
000
KV
交直流
穿墙套管
现场安装工艺
胶浸纸绝缘
1 000 kV
AC /DC
wall bushing
site installation process
resin impregnated paper insulation