摘要
介绍了多台现役机组采用的综合节能改造措施及实施效果,结合试验测试情况和长期运行后机组性能变化的实践经验,表明由《煤电节能减排升级与改造行动计划》提出的进一步降低现役机组供电煤耗的措施是可行的,但在具体方案的实施上需要结合实践经验,从设计、制造、运行全方位进行考虑。
The technical measures and implement effects of the comprehensive energy-saving modification of coal-fired units were conducted. Combined with the practical experiences, it was concluded that the measures used for further reducing the coal consumption of the Units in service presented in "Transformation and Upgrading Plan of Energy Conservation and Emission Reduction of Coal-Fired Units" were feasible. However, the consideration should be taken into the practical experience of design, manufacture and operation during the actual measure implementation.
出处
《热力透平》
2015年第3期156-160,共5页
Thermal Turbine
关键词
燃煤机组
综合节能改造
节能减排
煤耗
coabfired unit
comprehensive energy-saving modification
energy conservation and emission reduction
coal consumption