城市多跨简支体系梁桥整体顶升施工过程控制技术 被引量:3

The construction process control of integrally jack-up for the urban multi-span simply supported girder bridge system
下载PDF
导出
摘要 以成都市二环路北新立交高架桥整体顶升改造工程为例,介绍了桥梁同步顶升技术在城市立交改造工程中的应用,重点阐述了桥梁同步顶升技术的监测内容及测点布置方案,监测结果均满足要求。为多跨简支体系桥型整体顶升加固工程提供了一定的参考,同时也为相关工程改造设计及施工提供了有益经验。 Taking the reconstruction project of Bei Xin interchange viaduct in the second ring road of Chengdu as an example,bridges synchronous jack-up technique in the application of the city overpass project are introduced,which focuse on the monitoring of bridge sync jack-up technique content and layout of measuring points. The monitoring results meet the requirements. The multi-span simply supported girder bridge integrally jack-up provides certain reference for engineering,as well as provides the useful experience for relevant engineering design and construction.
作者 肖军
出处 《四川建筑科学研究》 北大核心 2015年第5期151-155,共5页 Sichuan Building Science
关键词 桥梁 简支梁体系 整体顶升 施工控制 bridge simply supported girder bridge integrally jack-up construction control
  • 相关文献

参考文献5

二级参考文献18

共引文献73

同被引文献5

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部