对渗水坝基进行水泥灌浆处理是解决坝基渗漏的有效方法。通过介绍某水库坝基防渗帷幕灌浆施工过程中,由于采用不同的钻孔压水试验方法而得到不同结果的工程实践,阐述目前水工建筑物水泥灌浆工程施工和质量检验中存在的问题,提出初步改进意见和探讨性建议。
Cement grouting processing is an effective method to solve the leakage of dam foundation .Through the intro-duction of a reservoir dam foundation seepage control curtain grouting construction process , due to the different of hole water pressure test method ,the paper gets different results of engineering practice ,expounds the current hydraulic struc-ture concrete problems which existing in the construction and quality inspection of grouting ,and puts forward the prelimi-nary improvement sand approachable suggestions .
出处
《资源环境与工程》
2015年第5期692-695,共4页
Resources Environment & Engineering
关键词
压水试验
岩体透水性
影响
water pressure test
permeability of rock mass