基于弹性补偿法的拱坝极限承载力分析方法 被引量:2

Analysis approach for ultimate bearing capacity of arch dams based on elastic compensation method
下载PDF
导出
摘要 针对弹塑性分析方法所采用的破坏模拟方式有失客观性且现有的失稳判据过多受人为因素干扰的问题,结合混凝土拱坝的结构特点,提出了基于Mohr-Coulomb屈服准则的单元承载比计算方法,探讨了通过承载比均匀度与基准承载比调整单元弹性模量的策略;基于塑性极限分析方法,提出了基于弹性补偿法的拱坝极限承载力分析方法。工程实例分析结果表明,采用该方法分析拱坝的极限承载力是合理和有效的。 In view of the facts that the failure simulation method adopted in elasto-plastic analysis lacks objectivity to a certain degree, and the currently used instability criteria are seriously influenced by artificial factors, a calculation method for the element bearing ratio, considering the characteristics of concrete arch dams, is put forward based on the Mohr-Coulomb yield criterion, and the adjustment of the element elastic modulus by means of the uniformity of the bearing ratio and the base bearing ratio is discussed. Then, an ultimate bearing capacity analysis method of arch dams based on the elastic compensation method and plastic limit analysis method is put forward. Analysis of an engineering case shows that this method is reasonable and effective.
出处 《水利水电科技进展》 CSCD 北大核心 2015年第6期78-81,118,共5页 Advances in Science and Technology of Water Resources
关键词 拱坝 极限承载力 弹性补偿法 承载比 弹性模量 arch dam ultimate bearing capacity elastic compensation method bearing ratio elastic modulus
  • 相关文献

参考文献9

二级参考文献80

共引文献75

同被引文献25

  • 1张伟,杨绿峰,韩晓凤.基于弹性补偿有限元法的无梁岔管安全评价[J].水利学报,2009,39(10):1175-1183. 被引量:13
  • 2杨璞,刘应华,袁鸿雁,岑章志.计算结构极限载荷的修正弹性补偿法[J].工程力学,2006,23(3):21-26. 被引量:9
  • 3黄岩松,周维垣,杨若琼,沈大利,林鹏.拉西瓦拱坝稳定性分析和评价[J].岩石力学与工程学报,2006,25(5):901-905. 被引量:12
  • 4MACKENZIE D, BOYLE J T. A method of estimating limit loads by iterative elastic analysis I: simple examples [ J ]. International Journal of Pressure Vessels & Piping, 1992, 53( 1 ) :77-95.
  • 5MACKENZIE D,SHI J,BOYLE J T.Finite element modeling for limit analysis by elastic compensation method [ J ].Computer & Structure, 1994,51 ( 4 ) : 403-410.
  • 6PONTER A R S,CARTER K F.Limit state solutions based on linear elastic solutions with spatially varying elastic modulus [ J ]. Computer Methods in Applied Mechanics and Engineering, 1997,140(3/4) :237-258.
  • 7YANG P, LIU Y, OHTAKE Y, et al. Limit analysis based on a modified elastic compensation method for nozzle-to-cylinder junctions [ J ].International Journal of Pressure Vessels and Piping,2005,82 (10) : 770-776.
  • 8SIMHA C H M, ADIBI-ASL R. Lower bound limit load estimation using a linear elastic analysis[J] .Journal of Pressure Vessel Technology, 2012, 134 (2) : 1207-1216.
  • 9洪晓林.拱坝坝体非线性分析与极限承载力的估算[D].南京:华东水利学院,1982.
  • 10李新民,王开治.拱坝极限承载力的一个计算方法[J].水利学报,1985,16(7):66-72.

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部