合同柔性与项目管理绩效改善实证研究:信任的影响 被引量:38

An Empirical Study on Relationship between Contract Flexibility and Project Management Performance in Construction Project:The Perspective of Trust between Owner and Contractor
原文传递
导出
摘要 合同柔性对工程项目管理绩效改善的积极作用已得到理论研究支持,但缺乏基于样本数据的实证检验。从业主与承包商信任的视角,本文构建了合同柔性、项目管理绩效及信任驱动/调节理论模型,探讨了信任在合同柔性与项目管理绩效关系中的作用。通过对233份调查问卷的统计数据分析,工程项目合同柔性对项目管理绩效改善具有显著作用,而关系要素信任是合同柔性形成的驱动变量而非合同柔性与绩效改善间的调节变量,且信任对绩效改善具有正向影响,研究发现具有一定的理论意义及工程实践价值。 The empirical tests on relationship between contract flexibility and project management performance are still rare. Based on the perspective of trust,this study constructs a theoretical model about contract flexibility,project management performance and the trust between owner and contractor,and introduces trust as a driving variable or moderator variable. With an empirical study of 233 questionnaires,the results show that: contract flexibility has significant effect on project management performance,and the trust between owner and contractor is a driver variable rather than moderator,the trust has significant positive impact on project management performance.The findings are of great value both in theory and practice.
作者 尹贻林 王垚
出处 《管理评论》 CSSCI 北大核心 2015年第9期151-162,共12页 Management Review
基金 国家自然科学基金面上项目(71472153 71172175)
关键词 合同柔性 项目管理绩效 信任 驱动变量 调节变量 contract flexibility project management performance trust driver variable moderator variable
  • 相关文献

参考文献42

  • 1Cantarelli C. C., Flyvbjerg B., Molin E. J. E. Cost Overruns in Large-scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness[J]. European Journal of Transport and Infrastructure, 2010,10(1):30-41.
  • 2Kim S. Risk Performance Indexes and Measurement Systems for Mega Construction Projects[J]. Journal of Civil Engineering and Management, 2011,16(4):586-594.
  • 3Wang S. Q., Tiong R. L. K., Ting S. K., et al. Evaluation and Management of Foreign Exchange and Revenue Risks in China BOT Projects[J]. Construction Management and Economics, 2000,18(2):197-207.
  • 4Jin X. H., Zhang G. M. Modeling Optimal Risk Allocation in PPP Projects Using Artificial Neural Networks[J]. International Journal of Project Management, 2011,29(5):591-603.
  • 5Songer A. D., Diekmann J., Pecsko R. S. Risk Analysis for Revenue Dependent Infrastructure Projects[J]. Construction Management and Economics, 1997,15(4):377-382.
  • 6Xu Y. L., Albert P. C. C., John F. Y. Y. Developing a Fuzzy Risk Allocation Model for PPP Projects in China[J]. Journal of Construction Engineering and Management, 2010,136(8):894-903.
  • 7Sayegh S. M. Risk Assessment and Allocation in the UAE Construction Industry[J]. International Journal of Project Management, 2008,26(4):431-438.
  • 8Helena Y., Harry J. S., Michanel H. The Role of Contractual Governance Flexibility in Realizing the Outcomes of Key Customer Relationships[J]. Journal of Business Venturing, 2001,16(1):529-555.
  • 9Carlos C., Marques R. C. Flexible Contracts to Cope with Uncertainty in Public-Private Partnerships[J]. International Journal of Project Management, 2013,31(2):473-483.
  • 10Andrew H., Walker G. The Dynamics of Inter-organizational Coordination[J]. Administrative Science Quarterly, 1984,29(4):598-621.

二级参考文献37

  • 1Wathne,K.H,J.B.Heide. Opportunism in Interfirm Relationships:Forms,Outcomes,and Solutions[J].Journal of Marketing,2000,(04):36-51.
  • 2Mesquita,L.F,T.H.Brush. Untangling Safeguard and Production Coordination Effects in Long-Term Buyer-Supplier Relationships[J].Academy of Management Journal,2008,(04):785-807.
  • 3Tangpong,C,K.T.Hung,Y.K.Ro. The Interaction Effect of Relational Norms and Agent Cooperativeness on Opportunism in Buyer-Supplier Relationships[J].Journal of Operations Management,2010,(05):398-414.
  • 4Wuyts,S,I.Geyskens. The Formation of Buyer-Supplier Relationships:Detailed Contract Drafting and Close Partner Selection[J].Journal of Marketing,2005,(04):103-117.doi:10.1509/jmkg.2005.69.4.103.
  • 5Carson,S.J,A.Madhok,T.Wu. Uncertainty,Opportunism,and Governance:The Effects of Volatility and Ambiguity on Formal and Relational Contracting[J].Academy of Management Journal,2006,(05):1058-1077.
  • 6Greenwald,A.G,A.R.Pratkanis,M.R.Leippe. Under What Conditions does Theory Obstruct Research Progress[J].Psychological Review,1986,(02):216-229.
  • 7Holmlund M. A Definition,Model,and Empirical Analysis of Business-to-Business Relationship Quality[J].International Journal of Service Industry Management,2008,(01):32-62.
  • 8Naudé,P,F.Buttle. Assessing Relationship Quality[J].Industrial Marketing Management,2000,(04):351-361.
  • 9Nielson,C.C. An Empirical Examination of the Role of 'Closeness' in Industrial Buyer-Seller Relationships[J].European Journal of Marketing,1997,(5/6):441-463.
  • 10Zand,D.E. Trust and Managerial Problem Solving[J].Administrative Science Quarterly,1972,(02):229-239.

共引文献12

同被引文献336

引证文献38

二级引证文献119

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部