井点降水失效情况下地下室集水坑深化施工技术

The Detailed Construction Technology for Catchpit in Basement When the Dewatering Engineering Failure
下载PDF
导出
摘要 在带有地下室的高层建筑工程中,一般布置一定数量的集水坑,在原地下水水位较高﹑且在施工过程中降水失效的情况下,常会存在降水后的地下水水位仍位于集水坑设计底标高以上,导致无法进行集水坑施工,进而影响整个建设工期的难题。以吉林省延吉市某高层住宅楼为例,提出降水失效情况下地下室集水坑的深化施工技术,并对其进行了施工验证。 In the project of high-rise building with basement, some catchpits are always been set. In the condition that the original underground water level is high and the dewatering engineering failure during the construction, there will be the problem that the level of underground water is still higher than the design elevation of bottom of the catchpit, so as to that the construction for eatchpit can not be continued, even make the whole construction period of the project being delayed. In this paper, authors take the project of high-rise building of a certain community in Yanji as an example, and put forward the further construction technology for catchpit in basement when the dewatering engineering does not work, and do the verification by construction.
机构地区 延边大学工学院
出处 《施工技术》 CAS 北大核心 2015年第19期59-61,共3页 Construction Technology
基金 延大土木工程建造教学资源库建设(802014010)
关键词 高层建筑 地下工程 集水坑 降水 施工技术 tall buildings underground catchpit dewatering construction
  • 相关文献

参考文献6

  • 1陆凤池,张伟玉,叶海桃.布置集水坑的构造筏板基础受力分析[J].建筑结构,2009,39(9):111-113. 被引量:1
  • 2黄慧芳.壁挂式集水坑整体施工方法[J].山西建筑,2012,38(32):105-106. 被引量:1
  • 3中国建筑科学研究院.GB50007-2011建筑地基基础设计规范[S].北京:中国建筑工业出版社,2011.
  • 4建筑施工手册(5版)[M].北京:中国建筑工业出版社.2012.
  • 5山西建筑工程(集团)总公司.GB50208-2011地下防水工程施工质量验收规范[S].北京:中国建筑工业出版社,2011.
  • 6GB50202-2002建筑地基基础工程施工质量验收规范[S].北京:中国建筑工业出版社,2002.

二级参考文献2

  • 1美国ANSYS公司驻京办事处.Ansys使用手册[M].
  • 2GB50010--2002混凝土结构设计规范[S].北京:中国建筑工业出版社,2002.

共引文献165

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部