岩滩水电站扩建工程地下厂房顶拱施工通道优化设计

Optimal Design of Access Tunnel for Construction of Underground Powerhouse Crown in Extension Project of Yantan Hydropower Station
下载PDF
导出
摘要 在岩滩水电站扩建工程地下厂房施工中,因顶拱开挖的施工进度直接关系到整个工程的进度,因此对厂房顶拱施工通道进行合理的布置,尽早完成该通道的施工,进行厂房顶拱的开挖,能有效缩短扩建工程第一台机组的发电时间,为项目直接带来经济效益。文中对优化设计方案进行了介绍。 The construction progress of access tunnel, for the underground powerhouse crown, directly decides the progress of the whole project. Therefore, this access tunnel is required to be arranged reasonably and completed as soon as possible, so as to shorten the construction period of the first unit and bring about direct economic benefit to the project. The paper makes a detailed introduction to the optimal design.
出处 《红水河》 2015年第5期15-19,共5页 Hongshui River
关键词 地下厂房 顶拱 施工通道 岩滩水电站扩建工程 underground powerhouse crown construction access tunnel extension project of Yantan hydropower station
  • 相关文献

参考文献3

  • 1康世荣,陈东山,赵端伟,等.水利水电工程施工组织设计手册[M].北京:水利电力出版社,1986.
  • 2DL/T5397-2007,水电工程施工组织设计规范[S].
  • 3广西电力工业勘察设计研究院.岩滩水电站扩建工程可行性研究报告[R].南宁:广西电力工业勘察设计研究院,2005.

共引文献33

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部